Wednesday, April 15, 2020

granny annex residential log cabin How to build quick a log home

Outside insulated log cabin
We can reach the required u values of the building regulations





 1st day, delivery of the packs, starting to build









 End of day one, roof rafters are positioned


 Day two: fixing roof rafters, placing pieces between rafters, fascia and gable boards

 Day three: prepare roof membrane and lath

 day four: tiles
 Day five: MCB and uprights, outside insulation
Day six to 10: Insulating, roof ceiling, electritian, water- waste water supply
Day eleven till fourteen: Trim, floor, staining.