Outside insulated log cabin
We can reach the required u values of the building regulations
1st day, delivery of the packs, starting to build
End of day one, roof rafters are positioned
Day two: fixing roof rafters, placing pieces between rafters, fascia and gable boards
Day three: prepare roof membrane and lath
day four: tiles
Day five: MCB and uprights, outside insulation
Day six to 10: Insulating, roof ceiling, electritian, water- waste water supply
Day eleven till fourteen: Trim, floor, staining.